Connect your MBW

Installation of your MBW is really just three simple steps:

1. Level Station

Make certain that the system is sitting steady on the floor and all 8 feet are touching. Verify that the system is sloped towards the drain, is ¼ bubble slope, and is level side to side per the factory settings.

2. Attach the Water Hoses

Connect the hot and cold water hoses. We recommend you use the hoses supplied by Meritech to ensure that you have adequate hot and cold water flowing to the system. This is important for water flow and to ensure a comfortable temperature for users. Do not hard pipe directly to the system as this may prevent future serviceability to the system.

3. Plug in the CleanTech® Station

Plugin the MBW Automated Boot Scrubber. Run a couple of cycles to check for leaks from the hoses. Do not hardwire the system electrical cord without having a way to disconnect the system from electrical source for future serviceability of the system.

After verifying there arent any leaks we can move on to installing the solution and you will be good to go!