There are three things that will ensure a successful CleanTech EVO installation.
- Standard 100-240 VAC electrical outlet
- Hot and cold water supply with a minimum flow rate of 4 gallons per minute (GPM)
- Standard 1 1/2" floor or sink drain for wastewater disposal
Utilities
- Hot and cold water supply providing 4 gallons per min with 40-80 PSI
- 100-250VAC electrical outlet
Supplied with system
- 2x Flexible hose for hot and cold water connections
Provided by facility
- P-Trap drain connecter for 11/2" drain tube exiting the rear of the system